Lark Street Infrastructure Project

Lark Street Rendering

LARK STREET UPDATES: 

  • Top-course asphalt paving was completed on Friday, November 17th. (11/17/23)
  • Various Updates and Anticipated Timelines (11/15/23)
    • Completion of curb & sidewalk reconstruction: Will be completed by November 21st.
    • Tree Plantings:  Trees were planted in early November.
    • Paving Top Course of Asphalt:  Lark Street to be paved on Wednesday, November 15th, Thursday, November 16th and Friday, November 17th.
    • Final Striping: Will be completed off-peak hours on November 20th and 21st .
    • Above-Ground Electrical Work, including decorative lights over roadway:  Completion by Mid-December
    • Special decorative/colored/textured asphalt (around Trees and along crosswalks): Will be completed in Spring 2024
    • To Summarize:  Substantial completion of project is anticipated by November 22nd and Final Completion of Miscellaneous Items will extend intermittently into Spring 2024.


  • Various Updates and Anticipated Timelines (10/23/23)
    • Completion of curb & sidewalk reconstruction is anticipated for Mid-November.
    • Tree Plantings anticipated to begin Early November.
    • Paving Top Course of Asphalt is anticipated for Mid-November (specific days are TBD, weather-dependent).
    • Signs, Bicycle Racks, Final Striping and Special Asphalt Detailing at Tree Planters and along Crosswalks: are anticipated for Late November.
    • Above-Ground Electrical Work is anticipated to be completed by Mid-December.
    • To Summarize:  Substantial completion of project is anticipated for Mid-November and Final Completion of Miscellaneous Items is anticipated by Mid-December.
  • Milling & First-Course Paving is completed. A final Top Course of asphalt will be placed toward the end of the project in October. Partial curb and sidewalk reconstruction is currently in progress. (9/1/23)
  • Cobblestones are currently in process of being removed from intersections. (08/16/23)
  • Milling and First Course of Paving currently scheduled to begin on Monday, August 21st.
  • Project mobilization is scheduled to begin on July 31st with work to begin on Monday, August 7th. 

The Lark Street Infrastructure Project is scheduled to begin in August 2023 and conclude by the end of Fall 2023. 
The scope of the project includes:

  • Restoration of the pavement (Mill and Fill).
  • Removal of cobblestone intersections.
  • Addition of stamped asphalt strips (for traffic calming).
  • Ensure ADA Compliance (ADA ramps & detectable warnings).
  • Replacement of Curb Ramps and Sidewalks as necessary.
  • Incorporate Sidewalk extensions or bumpouts to the extent practical.
  • Install Hi-Vis Crosswalks.
  • Replacement and planting of new trees.
  • Addition of strings lights across Lark Street.
  • Installation of new park benches, bike racks, and trash receptacles.
Lark St. Improvements Visual (PNG)
PROJECT BOUNDARIES
Lark Street Boundry Map
PROJECT DESIGN MAPS
  1. 1 Lark Street (Madison to Hamilton)
  2. 2 Lark Street (Hudson to Jay)
  3. 3 Lark Street (Lancaster to Chestnut)
  4. 4 Lark Street (State to Washington)