Beaver Creek Project Construction Schedule

Construction for the the Beaver Creek Clean River Project includes five phases beginning inoverview map Spring of 2021 until Project completion in December 2022. Please check this page for updates to the construction schedule, or sign up to receive updates.

Treatment Facility and Diversion Pipe


Timeframe

Work 

Impacts

April 7 - April 23Pre-construction, tree removals lane closures
May 3, 2021 - Fall 2022Excavation and tunneling Closure of road from TOAST Elementary to MLK Jr. Blvd. Temporary Traffic Pattern 


Lincoln Park Bowl Fields



Timeframe

Work 

Impacts

May 3, 2021 - Summer 2022Fill added. Construction staging and activities Closure of sports fields and Lincoln Park Road (south)
Summer 2022- Fall 2022Regrading and seeding of fieldsClosure of sports fields and Lincoln Park Road (south)


Lincoln Park Ravine



Timeframe

Work 

Impacts

April 7 - April 14Tree/brush removalReduced access
Summer 2021Grading ImprovementsReduced access
Fall 2022Reinstall Community GardenReestablished and improved
2022Design of Ravine GardenFuture Improvement


Third Ave and Pearl St.


Timeframe

Work 

Impacts

April 12 - April 16Pre-constructionLane closures
May 31 - July 2Installation of Diversion StructureLane and parking closures

Temporary Traffic Pattern at TOAST Elementary for duration of construction.

Temporary Traffic Pattern