Beaver Creek Project Construction 

Construction for the the Beaver Creek Clean River Project includes five phases beginning in Spring of 2021 until Project completion in December 2022. Please check this page for updates to the construction schedule, or sign up to receive updates. Construction activities will include soil testing and continuous air quality monitoring (shown in real time via PurpleAir on the right of this page).overview map

Two Week Construction Look Ahead

  1. Rebecca Caldon, P.E.

    Engineering
    Phone: 518-434-5104

Loading PurpleAir Widget...

Treatment Facility (Phase 5) and Diversion Pipe (Phase 3)

Timeframe

Work 

Impacts

May 10, 2021 - Fall 2022Excavation and tunneling Closure of road from TOAST Elementary to MLK Jr. Blvd. Temporary Traffic Pattern (shown below) 
June - July 2021

Underground Blasting


Daily blast causing vibration and noise near Lincoln Park. Sign up to receive alerts from APD on Nixel.


Lincoln Park Bowl Athletic Field (Phase 5)

Timeframe

Work 

Impacts

May 2021 - May 2022 Fill added. Regrading of fields and new grassClosure of eastern half of Bowl and Lincoln Park Road (south)
May 2021 - May 2023Fill added. Regrading of fields and new grass
Closure of southwest quarter of Bowl and Lincoln Park Road (south)
September 2021 - May 2023 Fill added. Regrading of fields and new grass
Closure of northwest quarter of Bowl and Lincoln Park Road (south)


Lincoln Park Ravine (Phase 3)


Timeframe

Work 

Impacts

Summer 2021 - Fall 2023Grading ImprovementsReduced access
Fall 2022Reinstall Community GardenReestablished and improved
2022Design of Ravine GardenFuture Improvement


Third Ave and Pearl St. (Phase 1)


Timeframe

Work 

Impacts

June 1 - July 9Installation of Diversion StructureLane and parking closures

Temporary Traffic Pattern at TOAST Elementary for Duration of Construction.

Temporary Traffic Pattern