Construction for the the Beaver Creek Clean River Project includes five phases beginning in Spring of 2021 until Project completion in December 2022. Please check this page for updates to the construction schedule, or sign up to receive updates.
Treatment Facility and Diversion Pipe
Timeframe
Work
Impacts
April 7 - April 23
Pre-construction, tree removals
lane closures
May 3, 2021 - Fall 2022
Excavation and tunneling
Closure of road from TOAST Elementary to MLK Jr. Blvd. Temporary Traffic Pattern
Lincoln Park Bowl Fields
Timeframe
Work
Impacts
May 3, 2021 - Summer 2022
Fill added. Construction staging and activities
Closure of sports fields and Lincoln Park Road (south)
Summer 2022- Fall 2022
Regrading and seeding of fields
Closure of sports fields and Lincoln Park Road (south)
Lincoln Park Ravine
Timeframe
Work
Impacts
April 7 - April 14
Tree/brush removal
Reduced access
Summer 2021
Grading Improvements
Reduced access
Fall 2022
Reinstall Community Garden
Reestablished and improved
2022
Design of Ravine Garden
Future Improvement
Third Ave and Pearl St.
Timeframe
Work
Impacts
April 12 - April 16
Pre-construction
Lane closures
May 31 - July 2
Installation of Diversion Structure
Lane and parking closures
Temporary Traffic Pattern at TOAST Elementary for duration of construction.